PROJECTS IN THE ENERGY INDUSTRY

Cementos Argos S.A.
Rio Claro Plant - 2011

Maintenance Superheater, Turbine and rack

PROBLEMA: General maintenance of the rack with its frontal axis affected by torsion, fissured bars and unadjusted chains. Overheating in the secondary lintel or out superheater and fouling of the turbine rotor.
SOLUCIÓN: Replacement of the frontal axis, bars, pins and rack lubrication system. Modification of superheater by shortening it, removing rotor, sandblasting and balancing.
RESULTADOS: better torque, lubrication, adequate operation of the chain, decrease of the superheated steam temperature and it improve the boiler cycle and optimization in the turbine efficiency and/or turbo to the generation.


Cementos Argos S.A. · Sogamoso Plant - 2009-2010

Installation of 77000 lbs/hr Dedini boiler



Smurfit Kappa Carton
Colombia – 2009

Installation of cooling tower Midwest Towers



Cementos Argos S.A. · Rioclaro Plant – 2009

Installation of raw water pipeline



Cementos Argos S.A. · Rioclaro Plant - 2008-2009

Installation of 77000 lbs/hr Dedini boiler



Cementos Argos S.A. · Yumbo Plant – 2007-2008

Installation of 77000 lbs/hr Dedini boiler



Tolcementos - 2002-2003

Installation of 2 Wartsila self-generating power plants

PROBLEM: High energy consumption during cement manufacturing.
SOLUTION: Installation of a self-generating power plant.
RESULTS: Reduction of cement’s production costs.